The group have been set the task of clearing the area which needs about 1000mm of top soil removing to allow for hardcore and concrete for the new extension









Ground work team led by Joshua Harte, Anthony Norris, Keiron Marsh, Conner O'Hara and Aiden Stentiford


Nearly there boys!

Michael struggling to use French tools!


After the shuttering was assembled we were able to begin the task of laying a membrane and polystyrne with a re-inforcing mesh.





The tampering and leveling of the concrete has been done in a day.  We have also included a french drain and will look to complete the drainage in front and past the extension in the next few days.